Boulevard Park District Extension



Download the bid ready version of the Boulevard Park plan here: VVSD Boulevard Park Plans


VVSD held a bid opening on December 13th, 2024. The results were approved at the Dec 17th Regular Board Meeting. The following bidders were awarded the contracts:

Schedule A (Mainline Construction): HCON

Schedule B: BJ’s Construction

Schedule C: BJ’s Construction

Schedule D: BJ’s Construction

Schedule E: BJ’s Construction

Schedule F: BJ’s Construction

November 2024 :

This project was advertised for public bid on November 19, 2024. The bid opening is scheduled for the 11th of December 2024. The plans that are posted for the public bid are available for review. Several contractors have expressed interest in submitting bids for the project and their teams may be in the neighborhood evaluating the site.

A Notice to Proceed is planned to authorize work to begin April 1st of 2025.

The District will host a Public Meeting in early 2025 and detailed project information will be provided at that time.


The Boulevard Park Project is a District Extension that aims to provide sanitary sewer service to more than 70 lots around the 1200 and 1400 blocks near S 124th St in Burien. More than 11,000 feet of pipe and over a dozen manholes have been proposed to improve the water quality and development opportunities in this area. Administered by the Department of Commerce, a Local Community Project has awarded significant grant funding for the design and construction of these sewers.

This work is projected to begin in the spring of 2025.

For more information on this and other projects, contact our Valley View Sewer District inspectors:

Luis Maldonado – luism@valleyviewsewer.org

Benjamin Gerding – benjaming@valleyviewsewer.org

Boulevard Park Sewer Ext Prelim 10.18.22